Case Study
Confidential Fortune 500 CompanyTurning a Tight Deadline Into a Headline
Marietta, Georgia, USA
The Challenge
Our confidential client had an immovable completion date that mandated a condensed time frame and various fast-tracking elements. The site sits next to the Chattahoochee National Forest, requiring an environmentally sensitive design and proper permitting.
The Design Solution
HKS designers implemented several fast-track techniques to meet the client’s schedule. We obtained a land disturbance permit in a two-month period and delivered end of schematic design. We issued an early foundation package and our construction manager provided real-time pricing and real-time input that included monitoring and taking advantage of market changes throughout the project.
The Design Impact
The final delivery was on-time, under budget and included a pre-cast parking garage.
Project Features
- 180,000 square feet
- Six-story Greenfield office building
- 500-car parking garage